Connecting a linear shower drain right next to a wall stud

When a shower drain sits extremely close to the wall framing, standard trap alignment becomes nearly impossible without cutting open the slab to shift the pipe. This spatial conflict prevents a clean tie-in to existing plumbing and leaves installers considering disruptive concrete work.

What people tried

Every workaround mentioned in the threads below. We haven’t tested any of them — and nobody here is claiming they worked.

  1. 1
    Using an offset linear drain model to align with the existing setup.
  2. 2
    Relying on a horizontal wet vent system if upstream fixtures allow.
  3. 3
    cutting open the concrete pad to shift the drain over
  4. 4
    removing rigid foam and moving 2x4 studs closer to the wall using spray foam
  5. 5
    using an offset adapter

In their words

Unedited, grouped by where they were said, most upvoted first within each place, each linked to the thread it came from.

r/Plumbing2 people · September 2026 – October 2026

“I’m trying to figure out a good way to tie in the drain and trap to the current configuration but nothing seems to be a good solution.”source ↗

Luke-__- · r/Plumbing · 1 upvotes

“Unfortunately as you can see in the photo the shower drain is really close to the 2x4 framing. 1 3/8" OC from the framing.”source ↗

“I'm a bit concerned the only solution is to cut open the pad and shift it over.”source ↗