How to do project planning in Office 365 without MS Project

Organizations often refuse to buy MS Project licenses, forcing teams to rely on basic tools like MS Planner for complex schedules. This creates a terrible user experience because Planner lacks adequate resource management and time tracking features, making it nearly impossible to manage large budgets effectively.

Overview
People affected4 accounts across 1 forum
Workarounds found4 items attempted
Community agreement400 total upvotes

What people tried

Every workaround mentioned in the threads below. We haven’t tested any of them — and nobody here is claiming they worked.

Found another way around this?

Share your steps and trade-offs so fellow engineers don't have to reinvent the wheel. No account required.

  1. 1
    Using alternative third-party project management tools like Smartsheet, Asana, or Monday.com
    Did this help you?
  2. 2
    Switching to Azure DevOps for development-focused workflows
    Did this help you?
  3. 3
    Combining Microsoft Lists and Power BI for custom reporting and Gantt charts
    Did this help you?
  4. 4
    Upgrading to expensive higher-tier licenses like Microsoft Project Plan 3 or 5
    Did this help you?
Tried another approach not listed above?+ Share your workaround ↑

In their words

Unedited, grouped by where they were said, most upvoted first within each place, each linked to the thread it came from.

r/projectmanagement4 people · September 2025

“Having spent 20mins using the basic, web-based version of this app, I'm sinking into a pit of depression.”source ↗

“Seriously though, where did everyone move onto for project planning in an Office365 dominated workplace? Help me out pls!”source ↗

ohsomacho · r/projectmanagement · 342 upvotes

“Everything out there refers to some older version of Planner or it's specific to Planner for Web vs Planner for Teams... it's a gigantic mess and a terrible user experience.”source ↗

blueberryfinn · r/projectmanagement · 24 upvotes

“I got muppets trying to manage a schedule for an $18 million dollar program using MS Planner. All because the Org doesn't want to spend money on MS Project licences supposedly.”source ↗

Mashiko4 · r/projectmanagement · 20 upvotes

“Go look at the dumpster fire that is time tracking in planner. I have no words.”source ↗

thisismyB0OMstick · r/projectmanagement · 11 upvotes